to present
LAX Terminals 4 and 5 structural renovation and retrofit
Los Angeles International Airport
A four-billion-dollar, multi-year flagship project to upgrade Terminals 4 and 5 before the 2028 Olympics. The terminals take in more than 15 buildings: three are fully demolished and rebuilt, and the rest get additions and a new seismic system.
Rehan's scope
- Reviewing and documenting the history of structural changes, and checking the existing lateral system and connections against current code forces.
- Laying out and sizing the new gravity and lateral systems from the analysis.
- Phasing the structural work around the airport's operating constraints during construction.
- Developing the strengthening scheme for the existing super- and substructure.